Wire scheme of Alp Grüm station
In the scheme above you can see how the individual wires traverse the
station of
Alp Grüm. One post catches the eye, it is positioned very far away
from the rails. This is done to prevent pedestrians from running
into it because it is right at the pedestrian crossing of the path
to the upper restaurant.
|
Changeover to the sharp turn This photo of the original shows the transition from normally suspended overhead wire to the stretched wire used during the turn. On the first post, both the upper and the lower wire are directly attached. On the middle post, the upper wire is directly attached but the lower wire is pulled to the side by a special attachment, consisting of a thinner part from the post and a thicker, curved, part connecting to the lower wire. The rear post only holds the upper wire and the lower wire hangs free during the whole turn, connected to the pole via supporting wires. All supporting wires that hold the lower wire are made of two parts, a thin part from the upper wire and a think, curved, part to the lower wire. This is done to prevent the pantograph from touching the supporting wires. |
|
Marking the positions of our poles
Dec 2003 |
|
The first portal is standing Alp Grüm in a later stage (Christmas 2004), A part of the overhead catenary has taken its place. In particular the turn after Alp Grüm. It showed that we have to, just as in reality, tie up the poles in the curve to keep them straight. |
|
The wire has been installed Situation 2006, Station Alp Grüm completely wired. Also the special overhead wire in the turn is well visible. The material we used for the horizontal wires is bronze, 0,7 mm thick. The wires have the complete length of the station so that we don't need any weldings. The little vertical wires are made of messing wire, 0,5 mm thick. That is a lot easier to solder and cut. In order to bridge the gap between two modules, we used short, ready made pieces by Sommerfeldt. They can be removed easily for transport. |
A short manual
For fastening the vertical wires we took the following approach;
|
Wire scheme of Campocologno station |
Campocologno under construction by Johan and Steef.
|
|
June 2006. The lower wires are ready, the upper wire and the connecting wires are still to come. |
|
April 2007. The overhead catenary is almost done. A few pieces on the shunting tracks still have to be done but due to lack of the right wire it can take a while.
Sunday 1 April 2007 we used the overhead catenary for the first time.
|
|
March 2008. De overhead wire can be shown at Rail.
All station tracks are under wire now. |
Tunnels ?
We did not make overhead wire everywhere in the tunnel. We omitted that
on all places where we had enough space to have the pantograph upright,
that would only have complicated things. An exception is the spiral.
Here the height till the track above is not enough and so we did attach
a thick wire to the ceiling using metal strips. We used electric
installation wire (1,5mm). Also directly behind all tunnel entrances we
used this wire to "catch" the pantograph. Mounting the wire
under the spiral was best done by putting the complete module upside down.
Then you can easily solder everything into place. To determine the position
of the wire we used a specially prepared wagon with a pencil mounted on top
of it. A spring held it to the ceiling while driving over the rails.
This gave a nice line on the ceiling which could be used for positioning when soldering.
|
|
|
|
|
|